Skip to content
The Windsor Castle Road (Route 1008) bridge, spanning Windsor Creek in Windsor Township, has been completed 30 days ahead of schedule.
Submitted photo – Plenary Walsh Keystone Partner
The Windsor Castle Road (Route 1008) bridge, spanning Windsor Creek in Windsor Township, has been completed 30 days ahead of schedule.
Author
PUBLISHED: | UPDATED:

The Windsor Castle Road (Route 1008) bridge, spanning Windsor Creek in Windsor Township, Berks County, that’s been under construction as part of the Pennsylvania Department of Transportation’s Rapid Bridge Replacement Project, is complete and open to traffic. Replacement of the bridge allows PennDOT to remove it from Berks County’s structurally deficient bridge list.

The original closure was scheduled for 75 days, but the project team was able to expedite construction and complete the project 30 days ahead of schedule.

The bridge reopened to traffic on Thursday, May 11. Replacement work was performed by C.H. & D. Enterprises Inc. of New Stanton, PA.

The new crossing is longer and wider than the one it replaced and is designed with a 100-year lifespan.

This bridge is referred to as JV-171 and is one out of the 558 bridges being replaced under the Rapid Bridge Replacement Project. JV references the joint-venture partnership between Walsh/Granite, which is leading construction for the entire project.

The Rapid Bridge Replacement Project is a public-private partnership (P3) between PennDOT and Plenary Walsh Keystone Partners (PWKP), under which PWKP will finance, design, replace, and maintain the bridges for 25 years. The P3 approach will allow PennDOT to replace the bridges more quickly while achieving significant savings and minimizing impact on motorists.

To see the bridges included in the statewide initiative and to learn more about the Rapid Bridge Replacement Project and P3 in Pennsylvania, visit www.p3forpa.pa.gov. Additional information on the project, the team, and how to bid on the project can be found at www.parapidbridges.com.